Geothermal Completed System Installs

Callanan Elementary Schools, Des Moines, Iowa
Total System 129 Bores (255 feet deep) with vault
Engineer - Farris Engineering
Contractor - Accurate Mechanical
General Contractor - Rochon

Table Mounds Schools, Dubuque, Iowa
100+ Bores (305 feet deep) (Subcontract Drilling)
Completed drilling/installation on 60 Bores
Geothermal Contractor - Brockway Mechanical
Mechanical Contractor - Geisler Brothers

University of Dubuque, Dubuque, Iowa
42 Bores (305 feet deep) (Subcontract Drilling)
Completed drilling/installation on 24 bores
Geothermal Contractor - Brockway Mechanical
Mechanical Contractor - Geisler Brothers

Epworth High School, Epworth, Iowa
Total System - 40 Bores (305 feet deep)
Engineer - Farris Engineering
Mechanical Contractor - Geisler Brothers

Kirkwood Book Store, Cedar Rapids, Iowa
Total System - 42 Bores (305 feet deep)
Mechanical Contractor - Bowker Mechanical

Britt Community School
230+ Holes - (100 feet deep) (Subcontract Drilling)
Mechanical Contractor - Brockway Mechanical

Lemme School, Iowa City, Iowa
60+ Bores (305 feet deep) (Subcontract Drilling)
Completed drilling for 30+ Bores
Engineer - Shive Hattery

Marengo Hospital
Total System - 18 Bores (305 feet deep)
Mechanical Contractor - Cunningham Mechanical

Sacred Heart Church/School, West Des Moines, Iowa
Total System - 132 Bores (305 feet deep) with two vaults
Completed drilling 2.5 months
Mechanical Contractor - Waldinger, Inc.

Peosta Elementary School, Peosta, Iowa
60 holes - (305 feet deep)
Engineer - Farris Engineering
Mechanical Contractor - Geisler Brothers

Clinton Schools
140 holes - (200 feet deep) (Subcontract Drilling)
Engineer - Farris Engineering

Dubuque Hempstead School
10 holes - (305 feet deep) (Subcontract Drilling)
Contractor - Saathoff, Inc.

Mount Vernon High School (Fall 2005)
127 holes - (305 feet deep)
Engineer - Design Engineer
Contractor - Klieman Construction
Mechanical Contractor - Bowker Mechanical

Monticello Resource Center (Fall 2005)
22 holes - (305 feet deep)
Contractor - Klieman Construction

Premier Bank, Dubuque, Iowa (Fall 2005)
Total System - 32 holes (305 feet deep)
Mechanical Contractor - Geisler Brothers